The Projects Civil, electrical and locally fabrication work was a bit long and completed work and took almost 5 months to complete. The next was the Hiring of Lead Team
The Heads of Five departments were selected and hired and were given tasks to complete their teams on the given Hierarchy, JDs were formulated in coordination with the team heads. The Target was to initiate and complete the hiring process in less than 1 month.
After the teams were hired and the work began for their first respective tasks i.e Branding Guidelines, Equipment testing and the first test run.
Oct 2019, The Day came and we aired our first signal in coordination with Paksats to test our signal strenght and BUC powers.
On the same day our first emblem was aired as a bug on the screen. The Higher management decided to air the transmission in March 2020.
The Journey of creating our FPC began. Keeping in view the budgets and we knew that first transmission would not be viewed widely, we decided to create multiple shows in a small budget. The First Quarter was planned and working started on first Morning Show:Aik aur Subh.
More than 15 shows were created to give the audience a flavor of what we are bringing for them. Our License category was Infotainment, therefore, the shows were planned with informational perspectives..
The list of our First quarter shows was including: